Current to 14 Oct 26Onboarding plan for Tarnbeck Insurance Brokers' Starter tier go-live on 30 Jan 2025, covering 15 users. Phase 1 is complete, Phase 2 (CRM field mapping) is in progress, and production handover is targeted for mid-February 2025. Contract end is 29 Jan 2026.
What it is: a customer-facing onboarding plan written by Callie Brennan, Implementation Consultant. It sets out three phases: credentials and access, setup and mapping, then production and handover.
Commits: Phase 3 lists three milestones: "Full production refresh delivered", "Admin trained and confident" and "Support escalation route confirmed". The target is mid-February 2025, with the contract running 30 Jan 2025 to 29 Jan 2026.
Not settled: the plan states no price, service levels, connector delivery dates or renewal terms. It is not an order form. It is a snapshot from 5 Feb 2025, so Phase 2 status is stale and the evidence does not show whether handover happened.
Note: the stored status is final, but the text describes work in progress, so it is a point-in-time plan, not a record of completion.
As found in this document
Current to 9 Oct 26- Date end29 Jan 2026Source: object_read:doc_171_007
- Date start30 Jan 2025Source: object_read:doc_171_007
- Phase 3 targetMid-February 2025Source: object_read:doc_171_007
- Phase 3 milestonesFull production refresh delivered; Admin trained and confident; Support escalation route confirmedFull production refresh delivered; Admin trained and confident; Support escalation route confirmed · Source: object_read:doc_171_007
- Users covered15 usersSource: object_read:doc_171_007
The document
Body
Tarnbeck Insurance Brokers - Onboarding Plan
Overview
Tarnbeck Insurance Brokers went live on 30 Jan 2025 with BB-Demo's Starter tier. This plan covers implementation through February 2025 for 15 users.
Phase 1: Credentials and system access (completed)
Week of: 30 Jan 2025
Status: Completed
We gathered admin credentials for your CRM and confirmed network access for the database connection.
Phase 2: Setup and mapping (current)
Week of: 5 Feb 2025
Status: In progress
Before we switch on the refresh, we'll map your CRM fields to the brain's schema. What I need from your side is confirmation of your field usage so the mapping comes out clean. We'll run a test load and check that the data counts match your source.
Phase 3: Production and handover
Target: Mid-February 2025
Your 15 users will log in to the brain. We'll hand over a setup note for your admin covering user management, refresh runs and basic troubleshooting.
Milestones:
- Full production refresh delivered
- Admin trained and confident
- Support escalation route confirmed
Key dates
- Contract start: 30 Jan 2025
- Contract end: 29 Jan 2026
Read the whole document (1,306 characters)
Contacts
- Implementation: Callie Brennan
- Customer Success: Daniel Okafor
Thanks, Callie